Project details

Client name:
Total Exploration and Production Nigeria Limited
Started
2010
Completed:
2012
Category:
Completed
Architect:
Saipem Ponticelli Desicon Consortium

The scope includes the design, engineering, procurement, supply, transportation, fabrication, construction, pre-commissioning and commissioning of the upgrade and assistance with start-up of the PLANT, and completion of performance testing of the Plant. the project covered the Obite treatment center, the Obagi flow station, the Gas supply unit (GSU) for the IPP, Ibewa production center and the interconnecting facilities.

General activities of the work were:

  • Management, Project Control and Administration
  • Design, Construction and Field Engineering
  • Procurement, Supply and Transportation
  • Assignment of COMPANY ITEMS or EARLY CONTRACTS
  • PLANT Construction and decommissioning including facilities for construction and decommissioning
  • Shutdown Activities
  • Pre-commissioning, commissioning and assistance to start-up
  • PERFORMANCE TESTS
  • Third party Inspection and certification

Desicon scope covered the full Electrical and Instrumentation construction, pre-commissioning, Commissioning and Start-up of Obite, Obagi clusters including Telecommunications installation works, some minot procurement and extensive commissioning support.